Unified Planning Work Program (UPWP)
The UPWP lists the transportation studies
and tasks to be performed by the MPO staff or a member
agency. Because the UPWP reflects local issues and
strategic priorities, the contents of UPWPs differ from
one metropolitan area to another. The UPWP covers a one-
to two-year period. It typically contains several
elements:
- The planning tasks (e.g., data collection and
analysis, public outreach, and preparation of the plan
and Transportation Improvement Program), the supporting
studies, and the products that will result from these
activities;
- All federally funded studies as well as all relevant
state and local planning activities conducted without
federal funds;
- Funding sources identified for each project;
- A schedule of activities; and
- The agency responsible for each task or study.
|